Aduoyo Kokise Water Supply Project
Project Title: Aduoyo Kokise Water Supply Project
Client: The Franciscan Sisters of St. Anna – Lwak, Siaya Region
Location within Country: Siaya
No. of Staff: 4
Professional Staff provided by Our Firm/Entity(profiles):
- Water Engineer
- Structural Engineer
- Environmentalist
- Surveyor
No of Staff-Months; Duration of Assignment: 60Man-months: 9 months
Start Date: (Month/Year): Feb 2019
Completion Date: On Going
Approximate Value of Service (Kshs): KShs. 2.5 million
Name of Associated Consultants: None
No of Months of Professional Staff provided by Associated Consultants: N/A
Name of Senior Staff (Project Director/Coordinator, Team Leader) Involved and Functions Performed:
- Eng. B.M Owitti – Water/Sanitation Engineer
- Pascal Okoth – Surveyor
- C.M Shanyuma – Structural Engineer
Narrative Description of project:
- Detailed design of Water Supply Systems.
- Tender document preparation.
- Construction supervision
Description of Actual Services Provided by Your Staff:
- Detailed design and Tender Documentation for the Water Supply Systems and construction supervision